SR 516 — Lake/Orange Expressway.

Under construction · as of Apr 9, 2026

“SR 516 Lake/Orange Expressway: eastern end past halfway, first traffic due spring 2027” — Aug 31, 2026.

The timeline

Where is it really?

Under construction

Now

CFX broke ground on the 4.4-mile Lake/Orange Expressway in Clermont, with CFX leadership, Lake County Commissioner Sean Parks and Orange County Mayor Jerry Demings.

Somewhere on our West Orange County map

Development · Aug 31, 2026

SR 516 Lake/Orange Expressway: eastern end past halfway, first traffic due spring 2027

The 4.4-mile toll connector between US 27 south of Clermont and SR 429 in Horizon West is well into construction on its eastern end — CFX's April 2026 status report puts the SR 429-to-county-line segment at 74.47% complete, with its contract running to late April 2027. In April, the CFX board awarded the final western piece, US 27 to Cook Road, to SEMA Construction and Mehta and Associates, so all three segments are now moving. CFX still lists a spring 2027 partial opening and full completion in early 2029, including a three-quarter-mile wireless EV-charging test stretch near US 27.

sourced ↗

Central Florida Expressway Authority — April 2026 monthly status report

Somewhere on our West Orange County map

Development · Aug 31, 2026

SR 516: the eastern segment is three-quarters built, and the middle segment is under way

CFX's April 2026 construction report puts Segment 3 (county line to S.R. 429, SEMA Construction) at 74.47% complete on a $231,042,075 contract that runs to April 27, 2027. Segment 2 (Cook Road to the county line, Prince Contracting, $141,133,517) started construction April 13, 2026. A correction to earlier records: the 58.5% figure reported for Segment 3 in February was the contract's time used, not work complete — the February report shows 68.12% complete.

sourced ↗

Central Florida Expressway Authority

Somewhere on our West Orange County map

Development · Aug 31, 2026

SR 516: CFX says the expressway opens spring 2027, with completion in early 2029

The agency's official project page lists construction start summer 2024, opening spring 2027 and completion early 2029 for the 4.4-mile Lake/Orange Expressway.

sourced ↗

Central Florida Expressway Authority

The archive

We’ve covered this 3 times since November 2024.

Oldest first · from @theorlandoreal on Instagram — each opens the original reel

From our comments

“You know what also helps with relieving congestion? Public transportation!!!”

“What about trains?”

@sarahjgs849 asked this in January 2026 — on the reel

Real comments from @theorlandoreal’s Instagram — each opens the original reel

Send this to someone

The page stays current — whoever opens it gets where it really stands, not where it stood when you sent it.

Opens for anyone. No app, no login.